Force Outage Rate (FOR) is computed using the following equation:

FOR = FOH/(FOH+SH)

Where;

Forced outage hours (FOH) is the number of hours a unit was in an unplanned outage state

Service hours (SH) is the number of hours a unit was in the in-service state. It does not include reserve shutdown hours.

One should be careful to note that the FOR is not a rate at all but rather an estimator for a probability.



« What are the Classification of Mini-hydro?

What are the General Classification of Hydro Power Plants? »