The Procedure, Requirements and Project Cycle in Mini-Hydropower Development in the Philippines

Last January 2006, we were invited to attend a conference/seminar about mini-hydropower experiences and its development in the Philippines. Speakers discussed lots of things and issues about this kind of power generation, including the requirements and time line for a green field project development.

Lately, I found a good reference/guide for mini-hydro project development published by the Department of Energy (DOE) itself. It provides a more comprehensive mini-hydropower project cycle, in the Philippine Setting, of course. It is tabulated below.

Step Time Required Remarks
1. Identify potential
site/s

Consult DOE, NEA, NPC
and NIA lists, project profiles or own investigation (LGU’s)

2. Apply for
non-exclusive reconnaissance permit

Minimum of 2 weeks

Application to DOE:
privileges / rights to study the area.
3. Conduct
reconnaissance study
minimum of 3 months
and maximum of 1 year including conduct of FS
Contract foreign or local
consultants or use own technical capabilities
4. Submit reconnaissance report
to DOE
DOE evaluates submitted report
and informs the developer of the results
5. If site looks feasible,
conduct feasibility study (FS)
Contract foreign or local
consultants or use own technical capabilities
6. Apply for Environmental
Compliance Certificate (ECC)
minimum of 6 months Application with DENR. note: EIS
or IEE are basic requirements
7. Apply for Water Rights Permit Application with NWRB. note: ECC
is a requirement
8. Negotiate PPA with NPC or
electric cooperatives
9. Land acquisition with concerned land owners
10. Finalize financing plan Apply for concessionary loans
from donor or financial assistance packages from financial institutions
11. LGU endorsement with concerned local government
unit
12. Apply for operating contract
and accreditation as PSGF
Application to DOE: DOE
evaluates and checks all the necessary documents
13. Tender for construction and
installation works and evaluate bids; negotiate and sign contracts
3 months Individual tenders for civil
construction, electrical works, and electro-mechanical equipment supply,
or turn-key project
14. Scheme construction minimum of 9 months Submission of quarterly progress
report to DOE
15 Commissioning and test runs 3 months In the presence of electricity
inspector and experts in mini-hydropower development
Total time required minimum of 24 months

Well, a two years for a development of new mini-hydropower plant is just the shortest possible time. And most of the time, base from most developers’ experience, this timeline is seldomly met.




Filed in: Hydro
Local date: December, 2008

»Next article in Hydro: The Dinorwig Pumped Storage Hydroelectric Plant

Search This Site

 
Web www.jcmiras.net

Sponsored Links

Archives (107 posts)


Translations

English flagItalian flagKorean flagChinese (Simplified) flagPortuguese flag
German flagFrench flagSpanish flagJapanese flagArabic flag
Russian flagHindi flagNorwegian flag  
By N2H